I. Public investment in infrastructure, urban engineering:

Lake landscape CX 2 was started on 09/01/2012

Contractor under construction lake landscape CX 2

Contractor lake landscape CX 1, CX 3
II. Public investment projects adjacent villa (lower level):
Tháng 7/2010 started the construction of adjacent base 541, the villa is the perfect facade. To date 12.03.2012, there were 10/15 package adjacent to complete the entire facade of the warrant. Pour the concrete floor has been completed 100%, as follows:
|
No. |
Construction items |
Completion rate |
|
1 |
Wall |
97% |
|
2 |
Warrants front |
73% |
|
3 |
Processing + mount railing, gates, metal roofing, steel roof plastic |
14% |
|
4 |
Water proof, heat or roofing |
16% |
|
5 |
Barriers |
61% |

The villa is complete and the roof

Các căn nhà liền kề đang hoàn thiện cổng, lan can

Adjacent buildings are speeding in your hand I/2012

The building adjacent samples