I. Public investment in infrastructure, urban engineering:
Lake landscape CX 2 was started on 09/01/2012
Contractor under construction lake landscape CX 2
Contractor lake landscape CX 1, CX 3
II. Public investment projects adjacent villa (lower level):
Tháng 7/2010 started the construction of adjacent base 541, the villa is the perfect facade. To date 12.03.2012, there were 10/15 package adjacent to complete the entire facade of the warrant. Pour the concrete floor has been completed 100%, as follows:
No. |
Construction items |
Completion rate |
1 |
Wall |
97% |
2 |
Warrants front |
73% |
3 |
Processing + mount railing, gates, metal roofing, steel roof plastic |
14% |
4 |
Water proof, heat or roofing |
16% |
5 |
Barriers |
61% |
The villa is complete and the roof
Các căn nhà liền kề đang hoàn thiện cổng, lan can
Adjacent buildings are speeding in your hand I/2012
The building adjacent samples
@2012 An Hung.,JSC. All rights reserved